FIXED INSTALLATION TESTING PROCEDURE
Our electrician will initially carry out a visual inspection of all installation components, such as the recording of all fuse types, the size of cables, the type of cables the size and method of erection. A visual inspection of all connections in distribution boards will also be carried out along with all final circuit accessories.
After the Preliminary visual inspection, various tests are carried out to determine the health of the fixed installation. The following test sequence is carried out using the latest electrical testing equipment:
Test 1 : Continuity of protective conductors Test 2 : Continuity of bonding conductors Test 3 : Ring final circuits conductors Test 4 : Insulation resistance test Test 5 : Barriers and enclosures Test 6 : Polarity testing Test 7 : Earth fault loop impedance Test 8 : Prospective fault current short circuit and earth fault Test 9 : Functional test
All results and data are stored on the testing equipment and palm top PC’s. The information is then downloaded onto specialized software for analysis by our electricians. The detailed reports and processed to NICEIC approval and issued on completion of testing. If there are any faults reported, these are categorized with a rating of 1 – 4, depending on the severity of the fault found. 1 being a fault found that is very severe and in need of urgent attention and 4 being an observation that does not comply with current regulations for a fixed installation and requires some remedial action.
|